PAAMCO Project Initiation & Planning begins (target completion: September 2015)
RFP issued / Vendor responses received and evaluated
Vendor demos at WUSTL for subject matter expert group​​​ evaluation
Vendor acquisition activities
Contract finalized with vendor - infoEd Global
Complete Project Planning
PAAMCO Project Execution begins (target completion: June 2018)
PAAMCO Project kick-off with selected vendor (target date: October 1)
​Conflict of Interest (COI) work stream begins (target completion: September 2016)
PAAM Vendor webinar demo for product introduction to WUSTL community at large
COI Analysis & Design begins
COI Build, Test & Train begins (target completion: September 2016)
Pre-Award & Award Management (PAAM) work stream begins (target completion: September 2017)
PAAM Analysis & Design begins (target completion: June 2016)
PAAM Build, Test & Train begins (target completion: September 2017)
COI into Production / Go Live
SPIN into production / Go Live
Sub-Award Management work stream begins (target completion: June 2018)
    • ​Sub-Award Mngt Analysis & Design begins (target completion: September 2017)
  • Sub-Award Mngt Build, Test & Train begins (target completion: June 2018)
  • PAAM project work completed
  • PAAM into Production / Go Live
  • Sub-Award Mngt into production / Go Live
  • PAAMCO Project Execution completed
  • PAAMCO Closing process begins (target completion: August 2018)
  • PAAMCO Project Complete
​​​ ​​​​​​​​​​​​​​​​​ ​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​